Circle Mountain Road Work to Begin

Share on RSS

 

Charlie Taraboletti
Work will get underway next week on the Circle Mountain Road Rehabilitation Project.  Director of Engineering, Micah Siemers says work starts on Tuesday.
 
The project consists of a mill and overlay of the existing asphalt road with some areas of full depth patching according to Siemers.  He says because of the winding, steep geometry of the road, the city of Bartlesville will close it through the duration of the project to all traffic.
 
Siemers said traffic signs will be installed on Tuesday. All Circle Mountain traffic will be required to use the back entrance off of North 3940 Road for access.
 
Construction is anticipated to take two months to complete depending on weather conditions.